....with some of the black frames in place on the outside along Johnson too.
Whoops, I meant Cook not Johnson.
BUILT The Wade Uses: condo, commercial Address: 1105 Pandora Avenue Municipality: Victoria Region: Downtown Victoria Storeys: 5 Condo units: (studio/bachelor, 1BR, 2BR, 3BR, penthouse, 2BR + den, junior 1BR, junior 2BR) Sales status: sold out / resales only |
Posted 19 November 2019 - 08:27 AM
....with some of the black frames in place on the outside along Johnson too.
Whoops, I meant Cook not Johnson.
Posted 24 November 2019 - 10:06 AM
Know it all.
Citified.ca is Victoria's most comprehensive research resource for new-build homes and commercial spaces.
Posted 24 November 2019 - 12:11 PM
Posted 24 November 2019 - 01:06 PM
Nice to see some progress but they have a LOT of work to do still. Even if the windows are installed by the new year looking at at least 6 months to build out 100+ units
At the beginning of October the developers told me that occupancy would not be before March or April if they started getting regular delivery of framing and glazing (the glazing subcontractor was promising bi-weekly deliveries and installation of glazing) and given how little work has been done in the last month and a half, I would expect that estimation is already out the window. Half of the windows already installed on the courtyard side were installed in the first week of November. The remaining were installed in the last week. This corresponds to the bi-weekly deliveries that the developers spoke of. No work in installing the glazing appears to have been done in the intervening week. Looking at the percent of the glazing delivered and installed in these two bi-weekly deliveries (about one eighth of the total window surface was installed in each of these deliveries), and extrapolating the time required to install the glazing for the full building, there would be at least another 6 weeks of actual work to complete the rest if they have the framing and glazing readily available. If there is one week of idle time between deliveries, this means 11 weeks until the full glazing is completed. Then once the glazing fully encloses the building they can do the interiors which will likely require another month per floor.
Posted 24 November 2019 - 01:23 PM
Posted 24 November 2019 - 04:07 PM
Posted 24 November 2019 - 04:29 PM
Who receives occupancy first: The Wade or Hudson Place One?
Posted 24 November 2019 - 11:21 PM
Who receives occupancy first: The Wade or Hudson Place One?
Posted 07 December 2019 - 03:44 AM
Went by the building site yesterday (December 6). They have installed almost all of the glazing on the Cook street side of the North building (old building) but still don't have the finish outside profiles. They were hard at work installing the profiles used to accept the glazing on the old portion on the Pandora side of the North building. The annex to the North building is however still a long way off, it looks like they only have the concrete structure and nothing more. On the courtyard side they still have less than half the glazing installed, all of it on the North building only and I was not able to discern the installation of profiles to accept any glazing on the South building, so it doesn't look like they have made any more progress in the glazing since the photos of November 17th posted by Scotto203.
Posted 07 December 2019 - 05:47 PM
Posted 08 December 2019 - 06:59 AM
Know it all.
Citified.ca is Victoria's most comprehensive research resource for new-build homes and commercial spaces.
Posted 08 December 2019 - 07:14 AM
Know it all.
Citified.ca is Victoria's most comprehensive research resource for new-build homes and commercial spaces.
Posted 19 December 2019 - 10:14 AM
It's going to be a cool building when complete...I'm just not sure anyone alive today is going to be able to enjoy it.
Posted 19 December 2019 - 11:07 AM
Have any other owners received official notice of a delay (outside of the newsletter they sent out in November)? I think the latest document I've signed says December completion, but I'm fairly sure that isn't happening
Posted 19 December 2019 - 11:10 AM
...I think the latest document I've signed says December completion...
Does that document specify December 2019?
Posted 19 December 2019 - 11:19 AM
Does that document specify December 2019?
Good point, maybe they left out the year entirely!
Posted 19 December 2019 - 11:25 AM
Posted 20 December 2019 - 03:53 AM
Have any other owners received official notice of a delay (outside of the newsletter they sent out in November)? I think the latest document I've signed says December completion, but I'm fairly sure that isn't happening
The last document signed by the buyers that I am aware of stated September 31, 2019 occupancy. There was then an amendment sent out, dated June 6, 2019, that set the occupancy at some time between November 1st 2019 and January 31st 2020. This was never signed off by buyer as best as I can tell. Subsequently there was a newsletter of November 2019 on the protected webpage (see below), but this too was not signed off by the buyers.
Does that document specify December 2019?
The November update reads:
OCCUPANCY:
The Wade is on budget, but due to curtainwall (window frame) delivery delays, we are now scheduled for a March 2020 occupancy permit.
0 members, 2 guests, 0 anonymous users