[Downtown Victoria] The Falls condo | 54m | 18- & 13-storeys | Built - completed in Aug 2009
#181
Posted 07 February 2007 - 01:15 PM
#182
Posted 07 February 2007 - 03:03 PM
Aaron
#183
Posted 16 March 2007 - 03:47 PM
Know it all.
Citified.ca is Victoria's most comprehensive research resource for new-build homes and commercial spaces.
#184
Posted 31 March 2007 - 07:26 PM
Not only a great location, but, as they excavate, they have rock to build on...
The hole gets deeper and parts of it are looking as if they are getting ready to put in footings.. Doug and Humbldt corner..
#185
Posted 01 April 2007 - 11:32 AM
#186
Posted 14 April 2007 - 07:36 PM
Footings poured at Douglas and Humboldt as well as the base for one pier..
Still doing rock excavation on other parts of site..
#187
Posted 30 April 2007 - 11:58 AM
Know it all.
Citified.ca is Victoria's most comprehensive research resource for new-build homes and commercial spaces.
#188
Posted 30 April 2007 - 01:51 PM
-City of Victoria website, 2009
#189
Posted 02 May 2007 - 10:32 PM
#190
Posted 09 May 2007 - 07:44 PM
Know it all.
Citified.ca is Victoria's most comprehensive research resource for new-build homes and commercial spaces.
#191
Posted 09 May 2007 - 09:36 PM
The marketing budgets of these projects sure absorb lots of cash...
Haven't heard about any Vic Council time being used for these signs as opposed to all the time put into the one's for Parkside????
#192
Posted 24 May 2007 - 07:32 PM
Base for the crane has been delivered and is in the laydown area... no sign of a start on the base for it despite perimeter footings completed along Douglas and parts of Humboldt and Courtney... Floor poured at Doug/Humboldt corner.. and many bases and some columns poured... still drilling and blasting
May 25, 26, 2007...
correction... There are 2 crane bases awaiting installation..
#193
Posted 25 May 2007 - 06:23 AM
#194
Posted 30 May 2007 - 04:03 PM
#195
Posted 30 May 2007 - 04:28 PM
Did anyone else get a Westbank flyer in the mail? It has construction updates for The Falls and Shutters.
-City of Victoria website, 2009
#196
Posted 30 May 2007 - 04:33 PM
385 000 for that one bedroom seems a little steep and I am sure that it is on the side showing in that pic Aastra just posted. I think that overhang part is concrete but the sidewalk will extend well away from it especially on the western side.
#197
Posted 30 May 2007 - 04:41 PM
#198
Posted 30 May 2007 - 04:45 PM
Did anyone else get a Westbank flyer in the mail? It has construction updates for The Falls and Shutters.
Yup, I got one.
#199
Posted 30 May 2007 - 04:57 PM
Did anyone else get a Westbank flyer in the mail? It has construction updates for The Falls and Shutters.
Yup, I got one.
Probably prepared 2 months ago.. they're well ahead of that report, and as of Monday they had gone around to the Courtney side with the perimeter footing.. lots of columns in place along the Douglas St. Side..
#200
Posted 14 June 2007 - 09:46 PM